WE Report

Lessons Learned

Lesson Learned





By: Lars Solvang

Report No.

2198

Discipline/Origin

Drilling
Own Experience

Well

Oselvar
A-1 H, A-2 H, A-3 HT2

Date created

2021/10/04
1525 days ago

Project Phase

Operational
Project Phase

LL Type/Classification

Operational
Negative

Borgland Dolphin


What happened in P&A:
H2S had formed in the annulus fluid.

What Was Planned

Cut tubing and circulate out annulus completion fluid, treated seawater.

What Was Learned

H2S scavenger should be added into the fluid during circulation.

What Actions Are Required

H2S scavenge and chemical pump system to be included in the planning.